"It took a while. A long while." That was how 06880 reported the reopening of the Sherwood Mill Pond footbridges on October 24. The tidal gate renovation is finished, and the path from the Old Mill Beach parking lot to Compo Cove is open to the public again.
On its own, that reopening is good news for one of the prettiest short walks in town. It also comes in the same month as several other Town projects that were funded separately and are wrapping up on their own schedules. Together they link downtown, the train station, Longshore and Compo Beach by sidewalk, which is the Town's stated goal for the largest of them. This November, a Westport walk can start downtown and end at the water without someone having to drive you there.
The Mill Pond link is back, with finishing work through Thanksgiving
Most of the Mill Pond project happened out of sight. The Town's October 2026 Infrastructure Projects Update lists the work as repairs to two tide gates and a spillway, a rebuilt wooden pier, four short sections of seawall reconstructed, and repairs to the longer seawall sections that remain. The Town also notes that working tide gates help manage the pond's water quality and water levels.
The walkway was due in the second week of October, and the equipment stored in the parking area was scheduled to leave in the third week. The Town puts full site restoration at "by Thanksgiving 2026," which this year falls on November 26. So the footbridges are open, but some finishing work around the edges may still be underway on your walk.
Nearby, Sherwood Mill Pond Preserve sits at 191 Hillspoint Road, on the old site of Allen's Clam House. The Town lists a short walking path, benches, educational signs and a canoe and kayak launch there, and says a volunteer committee actively manages and maintains it. Old Mill Beach, where the reopened path begins, is a 1.8-acre Town beach with limited parking and no restrooms or changing facilities. If you're out for more than an hour, plan accordingly.
Compo Road South is the spine that ties it together
The Mill Pond path is a short loop by the water. The Compo Road South sidewalk project is what connects that kind of walk to the rest of town.
The project covers about 6,500 linear feet of new or rebuilt sidewalk on Compo Road South, from Post Road East to Bridge Street. The Town describes two goals. One is to complete a bike and pedestrian route between downtown and the train station. The other is to create a continuous bike and pedestrian route from downtown to the Town's recreation areas at Longshore and Compo Beach.
As of the Town's September 30 update, the work was about 70% complete, with completion planned for November 2026. It is funded by the state through the Local Transportation Capital Improvement Program, and the Town says it follows the goals of a 2016 Road Safety Audit for this stretch of road. Until the finish date is confirmed, treat November as the Town's estimate. The Town asks walkers and drivers on the corridor to watch for active work zones.
Longshore Club Park and Evan Harding Point sit on this route at 260 Compo Road South. The Town lists the park at 169 acres, open 24 hours unless otherwise posted, with the Inn at Longshore, Evan Harding Point and the PAL rink among its facilities. The rink runs November through March, so the sidewalk is finishing just as the rink's season starts.
Where the route ends, the winter dog rules apply
Compo Beach, at 60 Compo Beach Road, is open all year, and the Town charges parking fees only from May 1 through September 30. In the off-season, the beach also allows dogs, which is the biggest change on many November walks. The general beach page uses older wording. The Parks & Recreation notice posted September 29, 2026 is the current version, and it applies from October 1, 2026 through March 31, 2027:
- Dogs are prohibited from the Pavilion, the playground and the walkways.
- Dogs must be leashed in all areas of the park except the designated off-leash area of the beach south of the Pavilion, which includes South Beach.
- Off-leash rules are posted at the entrance to the off-leash area.
- Owners must pick up after their dogs.
- Violations carry a $77 fine.
The same notice says animals are not allowed on Town athletic fields or playgrounds at any time. Because Luciano Park is made up entirely of an athletic field and a playground, dogs are not allowed anywhere in it. If your walk passes Luciano Park, go around it.
The waterfront work at the marina finishes on the same schedule
Compo Ned Dimes Marina is finishing a separate set of projects this fall. The pier replacement adds rebuilt piers, walkways and ramps, a new fuel dock, and ADA-compliant pathways from the parking area to the floating docks that work at any tide. The Town's September 30 update said the last electrical components for the docks were due in the first week of October and new security gates were expected in the fourth week.
The seawall project next to the piers is bigger. About 800 linear feet of old seawall is being replaced with an engineered armored revetment. About 1,000 cubic yards of stone, or 2,190 tons, has been placed so far, and the top will get roughly 800 linear feet of 6-inch concrete curb. That project is also estimated for November 2026. A third piece, a new Eversource transformer and electrical service for the marina buildings and the South Beach restrooms, is still under Eversource review. It goes out to bid after approval and has no completion date yet.
Here is where each walking-related project stood in the Town's update dated September 30, 2026:
| Project | What it adds for walkers | Status, Sept. 30 | Town's estimate |
|---|---|---|---|
| Mill Pond Tide Gates | Footbridges and path, Old Mill Beach lot to Compo Cove | Final phase; path since reopened | Site restoration by Thanksgiving |
| Compo Road South Sidewalks | Downtown and station to Longshore and Compo | About 70% complete | November 2026 |
| Ned Dimes Marina Piers | ADA pathways from the parking area to the docks | Nearing completion | Fall 2026 |
| Ned Dimes Marina Seawall | Armored revetment along about 800 feet of shoreline | Under construction | November 2026 |
| Cross Highway Sidewalk | Wakeman Town Farm to North Avenue | Under construction | October 2026 |
| Easton Road–Wisteria Lane | Rebuilt sidewalk and flashing-beacon crosswalk | Under construction | Mid-November 2026 |
Inland, the same pattern on Cross Highway and Easton Road
Away from the water, the same thing is happening on a smaller scale. The rebuilt Cross Highway bridge over Deadman Brook is open to traffic, with stone veneer, grading and landscaping still to finish. A new sidewalk on Cross Highway from Wakeman Town Farm to North Avenue connects to the existing sidewalk east of the bridge. When it's done, there will be a continuous walking route from North Avenue to Bayberry Lane. New ADA-compliant curb ramps are already in at the intersections.
On Easton Road, the sidewalk on the west side is being rebuilt from Pony Lane to Brooklawn Drive. A new crosswalk with a Rectangular Rapid Flashing Beacon is going in at Wisteria Lane. B & W Paving & Landscaping is the contractor, and the Town expects the work to finish by mid-November.
Wakeman Town Farm, at 134 Cross Highway, sits at the west end of the new Cross Highway sidewalk, and its November calendar has reasons to walk there:
- Fantastic Farmhands, a fall session for ages 6 to 10, meets Tuesdays from November 10 through December 15, 4:15 to 5:15 p.m., with farm tasks, animal care and outdoor time.
- A wine dinner at the farm is set for Thursday, November 19, at 7 p.m.
- The Thanksgiving pie sale closes orders Thursday, November 19, at 5 p.m. Pickup is Monday, November 23, from 4 to 7 p.m. at Earth Animal, 925 Post Road East.
The one link that stays broken
One crossing has no reopening date. The Jesup Road Bridge near Imperial Avenue was badly damaged on September 13 and is still closed. The Town considers the structure unsafe and plans to remove it. It has issued a request for proposals to bridge design engineering firms and is working on plans to improve traffic flow around Jesup Road, with no schedule announced yet. If your usual walk from downtown toward the Westport Library or the Imperial Avenue lot used that bridge, you'll need a different route until the Town announces a schedule.
Taken together, the Town's own list adds up to this. The Mill Pond path is open now. The Compo Road South sidewalk and the marina seawall are due this month. The Cross Highway and Easton Road sidewalks are wrapping up close behind. The Jesup Road Bridge stays closed while its replacement is still in design.
Waterfront access, walkability and how close a home is to Compo and Longshore are details we cover with every shoreline seller, and they get more specific once these routes are finished. If you'd like to know how your home's location shows up in today's market, The Leslie Clarke Team is glad to put together a thoughtful valuation. Request a Home Valuation.